Soufflet Negoce v Bunge SA [2009] EWHC 2454 (Comm). Readiness to load – GAFTA form 49 clause 9 – Notice of readiness (NOR)


Awofeso, Adebowale (2009) Soufflet Negoce v Bunge SA [2009] EWHC 2454 (Comm). Readiness to load – GAFTA form 49 clause 9 – Notice of readiness (NOR) Shipping & Trade Law, 9, (9), pp. 5-6.

Download

Full text not available from this repository.

Description/Abstract

The facts The contract was for the sale of 15,000 tons of feed barley, FOB Nikotera, Ukraine; delivery 9-22 October 2006 at buyers’ call; weight and quantity to be final as issued by a GAFTA approved surveyor. Terms were provided as to laytime, demurrage or despatch, with laytime to commence upon issue of a valid notice of readiness. The sale contract also incorporated the GAFTA form No 49.

Item Type: Article
Related URLs:
Subjects:
ePrint ID: 176771
Date :
Date Event
1 November 2009Published
Date Deposited: 10 Mar 2011 15:43
Last Modified: 18 Apr 2017 02:42
Further Information:Google Scholar
URI: http://eprints.soton.ac.uk/id/eprint/176771

Actions (login required)

View Item View Item