Since 1967 the real (net of inflation) discount rate used to assess public sector projects in the UK has changed four times: from 8% to a peak of 10%, then to 5%, then to 6%, and then to the current position of 3.5% for years 1–30 declining in increments to 1% by year 300. This paper argues that the trend is in the right direction, but the associated decision process remains inappropriate, because the rationale for the changes has been flawed. Many other countries use discount rates of 6% or more in decision processes which are probably even more inappropriate. The fundamental problem stems from attempts by economists to embed too many conflicting considerations in a discount rate which is used in a single hurdle rate test. A multiple test approach is needed to address all the issues that the associated decision processes need to consider. This paper offers a way forward based on alternative economics perspectives, operational research perspectives, and established practice in a project risk management context. A case-based example concerned with the disposal of intermediate level nuclear waste in the UK illustrates how it works, and the implications of current UK practice, suggesting a very different view of a decision a decade ago which is a topical again. The proposed framework should be of interest to anyone interested in public sector projects, in the UK and elsewhere, and its generalisation has implications for private sector projects and private public partnerships (PPPs). Generic project risk management processes concerned with the whole of the project life cycle could embed a generalised form.
investment appraisal, project selection, public expenditure, discounting, generic project risk management processes, nuclear waste disposal
373-384
Chapman, C.B.
a4f4805b-b67d-4c4c-856b-78e01a2c89a0
Ward, S.C.
ac1bf683-4186-44e7-9f5e-4193ee4d03cd
Klein, J.H.
639e04f0-059a-4566-9361-a4edda0dba7d
July 2006
Chapman, C.B.
a4f4805b-b67d-4c4c-856b-78e01a2c89a0
Ward, S.C.
ac1bf683-4186-44e7-9f5e-4193ee4d03cd
Klein, J.H.
639e04f0-059a-4566-9361-a4edda0dba7d
Chapman, C.B., Ward, S.C. and Klein, J.H.
(2006)
An optimised multiple test framework for project selection in the public sector, with a nuclear waste disposal case-based example.
International Journal of Project Management, 24 (7), .
(doi:10.1016/j.ijproman.2006.02.008).
Abstract
Since 1967 the real (net of inflation) discount rate used to assess public sector projects in the UK has changed four times: from 8% to a peak of 10%, then to 5%, then to 6%, and then to the current position of 3.5% for years 1–30 declining in increments to 1% by year 300. This paper argues that the trend is in the right direction, but the associated decision process remains inappropriate, because the rationale for the changes has been flawed. Many other countries use discount rates of 6% or more in decision processes which are probably even more inappropriate. The fundamental problem stems from attempts by economists to embed too many conflicting considerations in a discount rate which is used in a single hurdle rate test. A multiple test approach is needed to address all the issues that the associated decision processes need to consider. This paper offers a way forward based on alternative economics perspectives, operational research perspectives, and established practice in a project risk management context. A case-based example concerned with the disposal of intermediate level nuclear waste in the UK illustrates how it works, and the implications of current UK practice, suggesting a very different view of a decision a decade ago which is a topical again. The proposed framework should be of interest to anyone interested in public sector projects, in the UK and elsewhere, and its generalisation has implications for private sector projects and private public partnerships (PPPs). Generic project risk management processes concerned with the whole of the project life cycle could embed a generalised form.
This record has no associated files available for download.
More information
Published date: July 2006
Keywords:
investment appraisal, project selection, public expenditure, discounting, generic project risk management processes, nuclear waste disposal
Identifiers
Local EPrints ID: 37498
URI: http://eprints.soton.ac.uk/id/eprint/37498
ISSN: 0263-7863
PURE UUID: 5eb01669-bdce-4f3b-8dc1-b002554de8cb
Catalogue record
Date deposited: 20 Jun 2006
Last modified: 16 Mar 2024 02:34
Export record
Altmetrics
Contributors
Author:
S.C. Ward