The University of Southampton
University of Southampton Institutional Repository

Integrating renewable energy sources with the UK electricity grid through interconnection or energy storage systems

Integrating renewable energy sources with the UK electricity grid through interconnection or energy storage systems
Integrating renewable energy sources with the UK electricity grid through interconnection or energy storage systems
This thesis considers the generation and demand challenges of a 100% renewable UK electricity grid and how this can be addressed with interconnection or energy storage. Hourly demand and electricity generation profiles for a year have been constructed: Business as Usual with a yearly demand of 540TWh and Green Plus (rapid uptake of energy efficiency and green measures) with a demand of 390TWh. In addition, two extra scenarios based on the above have been considered with electrification of heating (air source heat pumps) and transportation. The resultant hourly imbalances have been used to calculate the interconnection and energy storage requirements. The calculated interconnector capacity required was found to be 60GW at a cost of GBP 58 billion for the BAU scenario. Energy storage capacity requirements vary depending on the selected technology. Rated capacity was estimated to be 14GW with storage capacity of 3TWh for pumped storage, 11GW and 2.3TWh for liquid air, and 65GW and 13.6TWh for hydrogen storage, at a cost of GBP 65, GBP 76 and GBP 45 billion respectively. This thesis indicates that storing hydrogen in underground caverns would offer the cheapest solution. However, whilst these technological solutions can address generation and demand imbalance in a fully renewable electricity grid, there remain barriers to each technology.

A further technological solution is to exploit the use of electric heat pumps for domestic heating and hot water, as well as the moderate uptake of electric vehicles. It is proposed that these technologies are used on a local scale to help integrate the additional renewable electricity generated within a pre-determined zone of the electricity network. Analysis has been carried out to determine the constraints in the UK network where renewable electricity generation is greater than local electricity demand. From this, consideration has been made to understand the real impact distributed energy storage in the form of heat pumps and electric vehicles could have. Results show that depending on the demand scenario and location on the network, there is the potential to accommodate up to 50% of the excess electricity generated.

Lastly, analysis was conducted on a hybrid technological solution which combines interconnector and energy storage capacity in order to ensure that demand is met year round. This analysis indicates that an optimal combination of a 37GW interconnector plus 11GW of hydrogen (cavern) storage at a cost of GBP 42 billion for the BAU scenario is possible. Likewise, for the GP scenario a 24GW interconnector plus 8.5GW of hydrogen (cavern) storage at a cost of GBP 28 billion was found to be optimal. This analysis shows that a hybrid solution provides a lower cost option than installing either one of the solutions separately.
Alexander, Marcus Joseph
b7ef3eb7-2580-447d-87d2-0dfde868dafa
Alexander, Marcus Joseph
b7ef3eb7-2580-447d-87d2-0dfde868dafa
James, Patrick
da0be14a-aa63-46a7-8646-a37f9a02a71b

Alexander, Marcus Joseph (2016) Integrating renewable energy sources with the UK electricity grid through interconnection or energy storage systems. University of Southampton, Faculty of Engineering and the Environment, Doctoral Thesis, 271pp.

Record type: Thesis (Doctoral)

Abstract

This thesis considers the generation and demand challenges of a 100% renewable UK electricity grid and how this can be addressed with interconnection or energy storage. Hourly demand and electricity generation profiles for a year have been constructed: Business as Usual with a yearly demand of 540TWh and Green Plus (rapid uptake of energy efficiency and green measures) with a demand of 390TWh. In addition, two extra scenarios based on the above have been considered with electrification of heating (air source heat pumps) and transportation. The resultant hourly imbalances have been used to calculate the interconnection and energy storage requirements. The calculated interconnector capacity required was found to be 60GW at a cost of GBP 58 billion for the BAU scenario. Energy storage capacity requirements vary depending on the selected technology. Rated capacity was estimated to be 14GW with storage capacity of 3TWh for pumped storage, 11GW and 2.3TWh for liquid air, and 65GW and 13.6TWh for hydrogen storage, at a cost of GBP 65, GBP 76 and GBP 45 billion respectively. This thesis indicates that storing hydrogen in underground caverns would offer the cheapest solution. However, whilst these technological solutions can address generation and demand imbalance in a fully renewable electricity grid, there remain barriers to each technology.

A further technological solution is to exploit the use of electric heat pumps for domestic heating and hot water, as well as the moderate uptake of electric vehicles. It is proposed that these technologies are used on a local scale to help integrate the additional renewable electricity generated within a pre-determined zone of the electricity network. Analysis has been carried out to determine the constraints in the UK network where renewable electricity generation is greater than local electricity demand. From this, consideration has been made to understand the real impact distributed energy storage in the form of heat pumps and electric vehicles could have. Results show that depending on the demand scenario and location on the network, there is the potential to accommodate up to 50% of the excess electricity generated.

Lastly, analysis was conducted on a hybrid technological solution which combines interconnector and energy storage capacity in order to ensure that demand is met year round. This analysis indicates that an optimal combination of a 37GW interconnector plus 11GW of hydrogen (cavern) storage at a cost of GBP 42 billion for the BAU scenario is possible. Likewise, for the GP scenario a 24GW interconnector plus 8.5GW of hydrogen (cavern) storage at a cost of GBP 28 billion was found to be optimal. This analysis shows that a hybrid solution provides a lower cost option than installing either one of the solutions separately.

Text
Final e-thesis for e-prints - Alexander 21241724.pdf - Other
Download (11MB)

More information

Published date: June 2016
Organisations: University of Southampton, Energy & Climate Change Group

Identifiers

Local EPrints ID: 397263
URI: http://eprints.soton.ac.uk/id/eprint/397263
PURE UUID: 4489f9e0-015d-46db-8574-cc7d9876a55c
ORCID for Patrick James: ORCID iD orcid.org/0000-0002-2694-7054

Catalogue record

Date deposited: 13 Jul 2016 13:59
Last modified: 15 Mar 2024 02:46

Export record

Contributors

Author: Marcus Joseph Alexander
Thesis advisor: Patrick James ORCID iD

Download statistics

Downloads from ePrints over the past year. Other digital versions may also be available to download e.g. from the publisher's website.

View more statistics

Atom RSS 1.0 RSS 2.0

Contact ePrints Soton: eprints@soton.ac.uk

ePrints Soton supports OAI 2.0 with a base URL of http://eprints.soton.ac.uk/cgi/oai2

This repository has been built using EPrints software, developed at the University of Southampton, but available to everyone to use.

We use cookies to ensure that we give you the best experience on our website. If you continue without changing your settings, we will assume that you are happy to receive cookies on the University of Southampton website.

×