The total social costs of constructing and operating a high-speed rail line using a case study of the Riyadh-Dammam Corridor, Saudi Arabia

The total social costs of constructing and operating a high-speed rail line using a case study of the Riyadh-Dammam Corridor, Saudi Arabia
The total social costs of constructing and operating a high-speed rail line using a case study of the Riyadh-Dammam Corridor, Saudi Arabia
Constructing High-Speed Rail technology between the Saudi Arabian cities starts raising many challenging issues of a different nature ranging from technical to operational, which require huge investments in infrastructure, operations, and maintenance. However, this paper develops a new methodology to calculate the total social costs of building a new HSR worldwide and applies this using the case study of the Riyadh-Dammam corridor in Saudi Arabia. This is done through a Spreadsheet Cost Model mainly based on Microsoft Excel that includes operator cost, user cost, and external cost. In order to determine the total social costs of a Riyadh-Dammam HSR line, the annual travel demand is forecasted of 13,205,212 passengers in the first year of operation. In this case, the gravity demand model is used to forecast the demand, as a function of independent variables for the cities alongside with the proposed line such as the population, GDP per capita, the generalized journey time, unemployment rate, years since opening the corridor, and the dummy variable. As a result, the total social costs of constructing and operating the proposed HSR line is €1,090,106,913 per year resulting from the sum of the following categories. First, the total operator cost (OC) is €859,797,307 per year, which is mainly based on the total infrastructure and rolling stock costs of €750,852,759 per year and €108,944,548 per year, respectively. Second, the total user cost is €216,769,247 per year resulting from the sum of total annual passenger access/egress time, waiting time, and in-vehicle time. Finally, the total external environmental cost is €13,540,359 per year resulting from the sum of average costs of noise and air pollution, climate change, and accident.
Almujibah, Hamad
c115c81c-e109-404e-823f-54697ed32497
Preston, John
ef81c42e-c896-4768-92d1-052662037f0b
Almujibah, Hamad
c115c81c-e109-404e-823f-54697ed32497
Preston, John
ef81c42e-c896-4768-92d1-052662037f0b

Almujibah, Hamad and Preston, John (2019) The total social costs of constructing and operating a high-speed rail line using a case study of the Riyadh-Dammam Corridor, Saudi Arabia. Frontiers in Built Environment, 5. (doi:10.3389/fbuil.2019.00079).

Record type: Article

Abstract

Constructing High-Speed Rail technology between the Saudi Arabian cities starts raising many challenging issues of a different nature ranging from technical to operational, which require huge investments in infrastructure, operations, and maintenance. However, this paper develops a new methodology to calculate the total social costs of building a new HSR worldwide and applies this using the case study of the Riyadh-Dammam corridor in Saudi Arabia. This is done through a Spreadsheet Cost Model mainly based on Microsoft Excel that includes operator cost, user cost, and external cost. In order to determine the total social costs of a Riyadh-Dammam HSR line, the annual travel demand is forecasted of 13,205,212 passengers in the first year of operation. In this case, the gravity demand model is used to forecast the demand, as a function of independent variables for the cities alongside with the proposed line such as the population, GDP per capita, the generalized journey time, unemployment rate, years since opening the corridor, and the dummy variable. As a result, the total social costs of constructing and operating the proposed HSR line is €1,090,106,913 per year resulting from the sum of the following categories. First, the total operator cost (OC) is €859,797,307 per year, which is mainly based on the total infrastructure and rolling stock costs of €750,852,759 per year and €108,944,548 per year, respectively. Second, the total user cost is €216,769,247 per year resulting from the sum of total annual passenger access/egress time, waiting time, and in-vehicle time. Finally, the total external environmental cost is €13,540,359 per year resulting from the sum of average costs of noise and air pollution, climate change, and accident.

Text
HSR-Saudi Arabia (Almujibah Hamad) - Accepted Manuscript
Available under License Creative Commons Attribution.
Download (1MB)
Text
fbuil-05-00079 - Version of Record
Available under License Creative Commons Attribution.
Download (1MB)

More information

Accepted/In Press date: 28 May 2019
e-pub ahead of print date: 27 June 2019

Identifiers

Local EPrints ID: 432782
URI: http://eprints.soton.ac.uk/id/eprint/432782
PURE UUID: eafc49fb-1df1-4781-b0e9-78f743a513b6
ORCID for John Preston: ORCID iD orcid.org/0000-0002-6866-049X

Catalogue record

Date deposited: 26 Jul 2019 16:30
Last modified: 16 Mar 2024 03:48

Export record

Altmetrics

Contributors

Author: Hamad Almujibah
Author: John Preston ORCID iD

Download statistics

Downloads from ePrints over the past year. Other digital versions may also be available to download e.g. from the publisher's website.

View more statistics

Atom RSS 1.0 RSS 2.0

Contact ePrints Soton: eprints@soton.ac.uk

ePrints Soton supports OAI 2.0 with a base URL of http://eprints.soton.ac.uk/cgi/oai2

This repository has been built using EPrints software, developed at the University of Southampton, but available to everyone to use.

We use cookies to ensure that we give you the best experience on our website. If you continue without changing your settings, we will assume that you are happy to receive cookies on the University of Southampton website.

×